Construction Schedule


Construction is scheduled to begin during the week of April 10.  Work is expected to be completed by mid June.  During the construction of the sidewalk, westbound Larpenteur Avenue will be reduced to one lane to facilitate construction.

Week of April 24 – Subgrade preparation and storm sewer work
Week of May 1 – Subgrade preparation and storm sewer work
Week of May 8 – Grading and sidewalk work


Overview

 
The City of Roseville is planning to add a sidewalk on the north side of Larpenteur Avenue from Galtier Street to the Ramsey County Dog Park.  The additional sidewalk will be a public safety improvement and will generally aid pedestrian travel throughout the neighborhood and city park land.  The concrete sidewalk will be 8 feet wide and will be installed adjacent to a new curb.  There will also be various storm sewer work to accommodate drainage in the area. 
 
The City is partnering with Ramsey County on this project and also received a Community Development Block Grant to help pay for the addition of the sidewalk to help create a safe pedestrian connection to the rest of Roseville’s pathways and sidewalks.

Bid Information


The bid opening was held at 1:00 p.m., Wednesday, March 1, 2017 at Roseville City Hall.  Bid information is available on Roseville's eGram page or the QuestCDN website, project number 4468211.