County Road B Utility Improvements Project

Overview


The City of Roseville will be making three sewer repairs on County Road B between Dale Street and Cohansey Street. The repairs are being done to replace and upgrade existing failing infrastructure. Work is being done at this time since Xcel Energy is replacing the gas main along County Road B between Lexington Avenue and Rice Street. By doing the projects at the same time, impacts to the public will be minimized. Additional information on the Xcel gas project can be found here.

The cost of this project is funded by City utility funds. There will be NO ASSESSMENTS for this work within the City of Roseville.

Schedule


The contractor will be taking measurements at Dale St. & CR B on Friday,
June 4.

This project is scheduled to start the week of June 28 with a duration of approximately 3 weeks. Our contractor will start on the Cohansey Blvd. intersection, then move to the Dale St. intersection. This schedule is dependent on coordination with the Xcel Energy gas line project and is subject to change.

Road Closures and Detours


In order to perform the work, County Road B will need to be detoured for all three sewer repairs. In addition, Dale Street will also need to be detoured for one of the repairs. Detour routes and schedules will be posted once they are determined. Access to homes and businesses will remain open. The detours and road closures will be done in conjunction with the Xcel gas project.

Related Projects


Xcel gas project