Roseville Public Works Construction Updates
Long Lake Lift Station Project
]https://www.cityofroseville.com/3767/Long-Lake-Lift-Station-Project]
Construction is anticipated to take approximately 1 month, with work to start as construction materials are received. Supply chain delays are a significant factor in this project schedule.
Fall 2023 – Current Start Date
June 2024 - Project Completion Deadline
?2023 Pathway Project?
[http://cityofroseville.com/3739/2023-Pathway-Project]
Lexington Avenue?
July 31 to August 17: Grading and Wall construction
Week of August 28: Pathway Paving, Concrete Ped Ramps
Marion Street
August 20 to 27: Utility Work
August 28 to mid-September: Grading and Concrete Sidewalk Construction
Mid-September: Roadway Milling and Paving
Cleveland Avenue
August: Small Utility Relocations - By Others
Late September to Mid-October: Retaining Wall and Pathway Construction
Please note that construction schedules are subject to change.
Other Roseville, Ramsey County and MnDOT projects can be found on the City’s Construction Projects webpage.
[http://www.cityofroseville.com/697/Construction-Projects]
* * * * * * *
This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:
http://www.cityofroseville.com/list.asp?mode=del [http://www.cityofroseville.com/list.asp?mode=del]