County Road B (West of Cleveland) Reconstruction Project [https://cityofroseville.com/3580/County-Road-B-Reconstruction-2024]
Week of September 23
-Grading of the trail and placement of the first lift of pavement is scheduled to begin on Monday.
-Mucking of the pond at the north end of Fulham is underway.
-The City Engineer will connect with residents along County Road B regarding restoration behind the new curb.
Sanitary Sewer Main Lining Project [https://cityofroseville.com/827/Sanitary-Sewer-Main-Lining]
Week of September 23
-The work is substantially complete. One line remains to be lined, and staff is working with the contractor to determine if the segment will be lined this winter or removed from the contract.
Other Roseville, Ramsey County and MnDOT projects can be found on the City’s construction projects webpage [http://www.cityofroseville.com/697/Construction-Projects] .
* * * * * * *
This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:
http://www.cityofroseville.com/list.asp?mode=del [http://www.cityofroseville.com/list.asp?mode=del]