Overview
The City of Falcon Heights manages a comprehensive Pavement Management Program which includes repaving several miles of local streets every two years. To see which streets are included in 2023, please see the proposed Project Map.
The majority of the proposed roadways will have the top layer of asphalt section removed and repaved. Spot curb and gutter repairs will also be done as part of this project. We expect very little impact to driveways on those streets as part of this project.
Garden Avenue is proposed to have more extensive work done, which would involve removal of all asphalt and re-construction of the roadway. At the November 9, 2022 City Council meeting, the Council approved moving forward with design Option 4 and Option 7. Both of these options include a sidewalk on the north side of the roadway and a reduced street width.
Option 4 (Segment 1 - Garden Ave - West of Holton Street):
Option 7 (Segment 2 - Garden Ave – Holton to Hamline):
Frequently asked questions for the Garden Avenue work are available here. Previously considered Garden Avenue Design Options are available here.
A surfaced pathway connection on Ruggles Avenue between Pascal and Holton is still under consideration.
Neighborhood Meeting
Previously, the City hosted a neighborhood meeting to discuss the project as a whole on October 5, 2022. The City also hosted two open houses, on April 5, 2022 and July 20, 2022, to discuss the Ruggles Street pathway proposal and Garden Avenue. The exhibits and handouts are posted on the right for review.
Schedule
Please note, this schedule is subject to change. Council Actions are denoted with CC and will take place at a public council meeting:
Winter 2022 – Final Design, CC Approve Plans and Order Advertisement for Bids
Spring 2023 – CC Accept Bids
Spring 2023 – Neighborhood Construction Meeting
Summer/Fall 2023 – Construction
Fall 2023 – Assessment Hearing
Spring 2024 – Final Restoration
Documents
Feasibility Report
Project Map
Garden Ave Map
Meetings
November 9, 2022 Council Meeting
Presentation
October 5, 2022
Handout
Presentation
July 20, 2022
Handout
Concept Summary
Concept Comparison Table
Layout - Concepts A and B (Snelling to Holton)
Layout - Concepts C and D (Snelling to Holton)
Layout - Concept E and F (Holton to Hamline)
Layout - Concepts G and Existing (Holton to Hamline)
April 5, 2022
Handout
Proposed 2023 PMP
Garden Ave - Existing
FH Elem. School - A
FH Elem. School - B
Garden/Holton - A
Garden/Holton - B