Welcome to Roseville Public Works Construction Projects Updates for 2021. The Public Works Department will be utilizing this platform throughout this year's construction season to help keep residents updated on the status of projects it expects to impact city streets. If you find this email subscription useful, please consider sharing it with a friend.
The following project webpages have been updated:
Cleveland Watermain
[https://www.cityofroseville.com/3529/Cleveland-Watermain-Improvements-Project]
Week of August 9 – The northbound lane of Cleveland Avenue will be milled on Thursday, August 12, and paved on Friday, August 13. The final layer of pavement will be installed.
Week of August 16 – Pavement markings will be installed and traffic control will be removed. Normal mail service will resume once traffic control is removed.
Snelling Avenue (TH51) & Lydia Avenue Signal Modification
[https://www.cityofroseville.com/3618/Snelling-Ave-Lydia-Ave-Signal-Modificati]
Friday August 6-Saturday August 7 - Work on the median in Snelling will take place. The southbound left turn lane to Lydia will be closed. The inside northbound thru lane on Snelling Avenue will be closed . All major intersection work should be completed on Saturday. All traffic control will be removed and all lanes will be fully opened to the new traffic configuration.
Week of August 9 - Permanent pavement markings will be installed.
* * * * * * *