Welcome to Roseville Public Works Construction Projects Updates for 2021. The Public Works Department will be utilizing this platform throughout this year's construction season to help keep residents updated on the status of projects it expects to impact city streets. If you find this email subscription useful, please consider sharing it with a friend.
The following project webpages have been updated:
Cleveland Watermain
[https://www.cityofroseville.com/3529/Cleveland-Watermain-Improvements-Project]
Week of June 14 – Watermain work will continue north of Langton Lake Drive. Brenner Avenue will remain closed.
Week of June 21- Watermain work will continue north of Langton Lake Drive. Brenner Avenue will remain closed. Restoration work will begin for areas south of Langton Lake Drive.
Closures/Detour
Brenner Avenue, just east of Cleveland will be closed for three weeks starting June 4. Access to residents east of this location will remain open.
2021 Pavement Management Project
[https://www.cityofroseville.com/2819/Pavement-Management-Project]
Construction has begun on Phases 1-4 with concrete and utility work. Milling the asphalt surface and paving has been scheduled:
Week of June 14 - Milling/Paving Area 1
Week of July 5 – Milling/Paving Area 2-4
* * * * * * *
This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at: