Roseville MN Homepage
Search

Notify Me

  1. Type your email address in the box and select Sign In.
  2. If you want to receive text messages enter your phone number and select Save.
  3. To subscribe or unsubscribe click Email icon and/or SMS icon next to the lists to which you wish to subscribe/unsubscribe.



Unless restricted by law, all correspondence to and from Roseville City government offices, including information submitted through electronic forms such as this one, may be public data subject to the Minnesota Data Practices Act and/or may be disclosed to third parties. However, contact information including email addresses and telephone numbers submitted on this webpage are private data and will not be released to the public.
Sender Name:
Roseville Public Works
Sent By:
(Automatically Sent By Website)
Send Date:
5/27/2022 4:08:29 PM
Email Subject:
Roseville Public Works - Projects Updates

Formatted HTML message

Public Works Update_2

Roseville Public Works Projects Updates

The following projects are ongoing in the City this week.  Please visit the webpages for additional information.

Lexington Watermain

Week of May 30 – Watermain work should be completed. Restoration work will begin with curb and sidewalk installation. 
Week of June 6 – Restoration work will continue bituminous paving. Temporary water will be removed.  All work should be completed by the end of the week and traffic control will be removed. 

Traffic on Lexington Avenue between Oakcrest Avenue and Woodhill Avenue is reduced to one lane in each direction by eliminating the center left turn lane. Traffic is shifted to the east to allow for watermain construction.

County Road B Watermain

Work on the project is underway.  Watermain work will continue through late June generally working from Lexington towards the west. Water services will be reconnected the week of June 6, with temporary services removed the week of June 13.

County Road B, between Hamline Avenue and Lexington Avenue, will be open to westbound traffic only.  Eastbound traffic is detoured. Please follow signs. Access to local residences will be maintained. This traffic control will be in place from May through the end of the project in September in conjunction with Xcel’s gas line work.

Pavement Management Project

Important project dates:

May 23 – Begin Minor Utility Work
June 6 – Begin Curb Removal and Replacement
June 6 – Begin Work at Larpenteur Trail
June 13 – Begin Work at Lexington Trail
July – Mill and Pave Roadways, Lawn Restoration
August – Simpson St Stormwater Improvements
TBD – Retaining Wall and Paving at County Road C2

As this project includes multiple neighborhoods, when the contractor starts work, you may not see them in your neighborhood right away. They may begin in a different area and work towards your street. Please contact City staff if you have concerns about specific dates such as graduation parties, family reunions, etc.

Snelling Avenue Median Cable Barrier Project

MnDOT continues their work on Snelling Avenue between County Road C and I-694.  Works consists of installing a new median cable barrier.  Lane restrictions will take place between 9:00 a.m. and 3:00 p.m. daily on the side the contractor is working.  Work will continue for southbound Snelling through mid-June. 

Ramsey County Projects

Please visit Ramsey County’s website for additional project information.  Work has begun on the County Road B2 project between Fairview Avenue and Snelling Avenue.  Lane shifts and lane reductions will be in place until the work is completed in June.

Ramsey County is also working with the railroad to replace the railroad signals and add gates on Victoria Street, just north of County Road C.  Lane shifts will be in place until the work is completed in a couple of weeks. 

Xcel Gas Project

Gas work continues on Hamline Avenue.  During the coming week, construction will occur in the following areas:

  • Hamline Avenue, between County Road B2 and Commerce Street:
    • Line installation and material staging.
    • Shifting lanes, two-way traffic allowed.
  • Hamline Avenue, between Commerce Street and County Road B:
    • Line installation and material staging.
    • One-way southbound only traffic.
  • Intersection of County Road B and Hamline Avenue:
    • Line installation and material staging.
    • Shifting lanes and lane closures.
  • County Road B, between Hamline and Lexington Avenues:
    • Line installation and material staging.
    • One-way westbound only traffic.

Please note that construction schedules are subject to change.

Other Roseville, Ramsey County and MnDOT projects can be found on the city’s construction projects webpage.

* * * * * * *

This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:

http://www.cityofroseville.com/list.asp?mode=del

Plain text message

Roseville Public Works Projects Updates
The following projects are ongoing in the City this week. Please visit the webpages for additional information.

Lexington Watermain
[https://www.cityofroseville.com/3642/Lexington-Avenue-Watermain-Improvements]
Week of May 30 – Watermain work should be completed. Restoration work will begin with curb and sidewalk installation.
Week of June 6 – Restoration work will continue bituminous paving. Temporary water will be removed. All work should be completed by the end of the week and traffic control will be removed.

Traffic on Lexington Avenue between Oakcrest Avenue and Woodhill Avenue is reduced to one lane in each direction by eliminating the center left turn lane. Traffic is shifted to the east to allow for watermain construction.

County Road B Watermain
[http://www.cityofroseville.com/3643/County-Road-B-Watermain-Improvements]
Work on the project is underway. Watermain work will continue through late June generally working from Lexington towards the west. Water services will be reconnected the week of June 6, with temporary services removed the week of June 13.

County Road B, between Hamline Avenue and Lexington Avenue, will be open to westbound traffic only. Eastbound traffic is detoured. Please follow signs. Access to local residences will be maintained. This traffic control will be in place from May through the end of the project in September in conjunction with Xcel’s gas line work.

Pavement Management Project
[http://cityofroseville.com/pmp]
Important project dates:
May 23 – Begin Minor Utility Work
June 6 – Begin Curb Removal and Replacement
June 6 – Begin Work at Larpenteur Trail
June 13 – Begin Work at Lexington Trail
July – Mill and Pave Roadways, Lawn Restoration
August – Simpson St Stormwater Improvements
TBD – Retaining Wall and Paving at County Road C2

As this project includes multiple neighborhoods, when the contractor starts work, you may not see them in your neighborhood right away. They may begin in a different area and work towards your street.

Please contact City staff if you have concerns about specific dates such as graduation parties, family reunions, etc.

Snelling Avenue Median Cable Barrier Project
[http://www.dot.state.mn.us/metro/projects/hwy51roseville-ardenhills]
MnDOT continues to work on Snelling Avenue between County Road C and I-694. Works consists of installing a new median cable barrier. Lane restrictions will take place between 9:00 a.m. and 3:00 p.m. daily on the side the contractor is working. Work will continue for southbound Snelling through mid-June.

Ramsey County Projects
[https://www.ramseycounty.us/residents/roads-transportation/current-roadwork/2022-road-construction-maintenance]
Please visit Ramsey County’s website for additional project information. Work has begun on the County Road B2 project between Fairview Avenue and Snelling Avenue. Lane shifts and lane reductions will be in place until the work is completed in June.

Ramsey County is also working with the railroad to replace the railroad signals and add gates on Victoria Street, just north of County Road C. Lane shifts will be in place until the work is completed in a couple of weeks.

Xcel Gas Project
[https://www.xcelenergynemetrogasproject.com]
Gas work continues on Hamline Avenue. During the coming week, construction will occur in the following areas:

Hamline Avenue, between County Road B2 and Commerce Street.
Line installation and material staging.
Shifting lanes, two-way traffic allowed.

Hamline Avenue, between Commerce Street and County Road B.
Line installation and material staging.
One-way southbound only traffic.

Intersection of County Road B and Hamline Avenue.
Line installation and material staging.
Shifting lanes and lane closures.

County Road B, between Hamline and Lexington Avenues.
Line installation and material staging.
One-way westbound only traffic.

Please note that construction schedules are subject to change.

Other Roseville, Ramsey County and MnDOT projects can be found on the city’s construction projects webpage.
[http://www.cityofroseville.com/697/Construction-Projects]

* * * * * * *

This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:
http://www.cityofroseville.com/list.asp?mode=del [http://www.cityofroseville.com/list.asp?mode=del]

SMS message

Updates have been made to the City of Roseville Public Works Projects webpages. They can be accessed at www.cityofroseville.com/construction.
  1. Roseville MN Homepage

Contact Us

  1. Roseville City Hall

  2. 2660 Civic Center Drive

  3. Roseville, MN 55113


  4. Monday - Friday
    8:00 a.m. - 4:30 p.m.


  5. Phone: 651-792-7000

  6. Email Us

<---- Userway script----->
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow