Roseville MN Homepage
Search

Notify Me

  1. Type your email address in the box and select Sign In.
  2. If you want to receive text messages enter your phone number and select Save.
  3. To subscribe or unsubscribe click Email icon and/or SMS icon next to the lists to which you wish to subscribe/unsubscribe.



Unless restricted by law, all correspondence to and from Roseville City government offices, including information submitted through electronic forms such as this one, may be public data subject to the Minnesota Data Practices Act and/or may be disclosed to third parties. However, contact information including email addresses and telephone numbers submitted on this webpage are private data and will not be released to the public.
Sender Name:
Roseville Public Works
Sent By:
(Automatically Sent By Website)
Send Date:
6/3/2022 4:22:37 PM
Email Subject:
Roseville Public Works - Projects Updates

Formatted HTML message

Public Works Update_2

Roseville Public Works Projects Updates

The following projects are ongoing in the City this week.  Please visit the webpages for additional information.

Lexington Watermain

Week of June 6 – Final restoration work and cleanup will take place.  All work should be completed by Wednesday, June 8, and traffic control will be removed.

Traffic on Lexington Avenue between Oakcrest Avenue and Woodhill Avenue is reduced to one lane in each direction by eliminating the center left turn lane.  All traffic control is scheduled to be removed June 8.

County Road B Watermain

Week of June 6 - Xcel Gas will finalize removing gas main.  Water services will be reconnected and temporary water will be removed.  All work related to the City’s watermain work should be completed.

Xcel’s gas project will begin later this summer and should be completed by late September.  The City will work with Xcel to maintain the work site prior to Xcel gas main replacement.  All restoration of curb, roads and turf will be done after the gas main is installed later this summer. 

In 2023, the City will replace the watermain on County Road B between Snelling Avenue and Hamline Avenue in conjunction with Ramsey County’s resurfacing project.

Pavement Management Project

Important project dates:

May 23 – Begin Minor Utility Work
June 6 – Begin Curb Removal and Replacement
June 6 – Begin Work at Larpenteur Trail
June 13 – Begin Work at Lexington Trail
July – Mill and Pave Roadways, Lawn Restoration
August – Simpson St Stormwater Improvements
TBD – Retaining Wall and Paving at County Road C2

As this project includes multiple neighborhoods, when the contractor starts work, you may not see them in your neighborhood right away. They may begin in a different area and work towards your street. Please contact City staff if you have concerns about specific dates such as graduation parties, family reunions, etc.

Snelling Avenue Median Cable Barrier Project

MnDOT continues their work on Snelling Avenue between County Road C and I-694.  Works consists of installing a new median cable barrier.  Lane restrictions will take place between 9:00 a.m. and 3:00 p.m. daily on the side the contractor is working.  Work will continue for southbound Snelling through mid-June. 

Ramsey County Projects

Please visit Ramsey County’s website for additional project information.  

Work on the County Road B2 project between Fairview Avenue and Snelling Avenue is completed.

Railroad work on the Victoria Street, just north of County Road C is completed. 

Intersection and signal work at Lexington Avenue and County Road B2 is scheduled to begin on June 13. Full closure of the intersection is scheduled to begin on June 13 for up to two weeks. Please follow posted detours. After that time, Lexington Avenue will be open to traffic and portions of County Road B2 will be closed until the project is completed in mid-August.

Xcel Gas Project

Gas work continues on Hamline Avenue.  In response to “cut-through” traffic, Xcel will install road closure signage at Burke Avenue and Eldridge Avenue along their detour route. Local resident access will be maintained.

During the coming week, construction will occur in the following areas:

  • Hamline Avenue, between County Road B2 and Commerce Street:
    • Line installation and material staging.
    • Shifting lanes, two-way traffic allowed.
  • Hamline Avenue, between Commerce Street and County Road B:
    • Line installation and material staging.
    • One-way southbound only traffic.
  • Intersection of County Road B and Hamline Avenue:
    • Line installation and material staging.
    • Shifting lanes and lane closures.
  • County Road B, between Hamline and Lexington Avenues:
    • Line installation and material staging.
    • One-way westbound only traffic.

Please note that construction schedules are subject to change.

Other Roseville, Ramsey County and MnDOT projects can be found on the city’s construction projects webpage.

* * * * * * *

This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:

http://www.cityofroseville.com/list.asp?mode=del

Plain text message

Roseville Public Works Projects Updates
The following projects are ongoing in the City this week. Please visit the webpages for additional information.

Lexington Watermain
[https://www.cityofroseville.com/3642/Lexington-Avenue-Watermain-Improvements]
Week of June 6 – Final restoration work and cleanup will take place. All work should be completed by Wednesday, June 8, and traffic control will be removed.

Traffic on Lexington Avenue between Oakcrest Avenue and Woodhill Avenue is reduced to one lane in each direction by eliminating the center left turn lane. All traffic control is scheduled to be removed June 8.

County Road B Watermain
[http://www.cityofroseville.com/3643/County-Road-B-Watermain-Improvements]
Week of June 6 - Xcel Gas will finalize removing gas main. Water services will be reconnected and temporary water will be removed. All work related to the City’s watermain work should be completed.

Xcel’s gas project will begin later this summer and should be completed by late September. The City will work with Xcel to maintain the work site prior to Xcel gas main replacement. All restoration of curb, roads and turf will be done after the gas main is installed later this summer.

In 2023, the City will replace the watermain on County Road B between Snelling Avenue and Hamline Avenue in conjunction with Ramsey County’s resurfacing project.

Pavement Management Project
[http://cityofroseville.com/pmp]
Important project dates:
May 23 – Begin Minor Utility Work
June 6 – Begin Curb Removal and Replacement
June 6 – Begin Work at Larpenteur Trail
June 13 – Begin Work at Lexington Trail
July – Mill and Pave Roadways, Lawn Restoration
August – Simpson St Stormwater Improvements
TBD – Retaining Wall and Paving at County Road C2

As this project includes multiple neighborhoods, when the contractor starts work, you may not see them in your neighborhood right away. They may begin in a different area and work towards your street.

Please contact City staff if you have concerns about specific dates such as graduation parties, family reunions, etc.

Snelling Avenue Median Cable Barrier Project
[http://www.dot.state.mn.us/metro/projects/hwy51roseville-ardenhills]
MnDOT continues to work on Snelling Avenue between County Road C and I-694. Works consists of installing a new median cable barrier. Lane restrictions will take place between 9:00 a.m. and 3:00 p.m. daily on the side the contractor is working. Work will continue for southbound Snelling through mid-June.

Ramsey County Projects
[https://www.ramseycounty.us/residents/roads-transportation/current-roadwork/2022-road-construction-maintenance]
Please visit Ramsey County’s website for additional project information.
Work on the County Road B2 project between Fairview Avenue and Snelling Avenue is completed.

Railroad work on the Victoria Street, just north of County Road C is completed.
Intersection and signal work at Lexington Avenue and County Road B2 is scheduled to begin on June 13. Full closure of the intersection is scheduled to begin on June 13 for up to two weeks. Please follow posted detours. After that time, Lexington Avenue will be open to traffic and portions of County Road B2 will be closed until the project is completed in mid-August.

Xcel Gas Project
[https://www.xcelenergynemetrogasproject.com]
Gas work continues on Hamline Avenue. In response to “cut-through” traffic, Xcel will install road closure signage at Burke Avenue and Eldridge Avenue along their detour route. Local resident access will be maintained. During the coming week, construction will occur in the following areas:

Hamline Avenue, between County Road B2 and Commerce Street.
Line installation and material staging.
Shifting lanes, two-way traffic allowed.

Hamline Avenue, between Commerce Street and County Road B.
Line installation and material staging.
One-way southbound only traffic.

Intersection of County Road B and Hamline Avenue.
Line installation and material staging.
Shifting lanes and lane closures.

County Road B, between Hamline and Lexington Avenues.
Line installation and material staging.
One-way westbound only traffic.

Please note that construction schedules are subject to change.

Other Roseville, Ramsey County and MnDOT projects can be found on the city’s construction projects webpage.
[http://www.cityofroseville.com/697/Construction-Projects]

* * * * * * *

This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:
http://www.cityofroseville.com/list.asp?mode=del [http://www.cityofroseville.com/list.asp?mode=del]

SMS message

Updates have been made to the City of Roseville Public Works Projects webpages. They can be accessed at www.cityofroseville.com/construction.
  1. Roseville MN Homepage

Contact Us

  1. Roseville City Hall

  2. 2660 Civic Center Drive

  3. Roseville, MN 55113


  4. Monday - Friday
    8:00 a.m. - 4:30 p.m.


  5. Phone: 651-792-7000

  6. Email Us

<---- Userway script----->
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow