Roseville Public Works Projects Updates
The following projects are ongoing in the City this week. Visit the individual project webpages for additional information. Please note that construction schedules are subject to change.
Pavement Management Project
[http://cityofroseville.com/pmp]
Important project dates:
Week of July 25 - Paving Lexington Avenue pathway
Week of August 1 – Retaining Wall on County Road C2
August – Stormwater Improvements on Simpson Street
September - Milling and Paving Burke Avenue, Simpson Street and County Road C2
As this project includes multiple neighborhoods, when the contractor starts work, you may not see them in your neighborhood right away. They may begin in a different area and work towards your street. Please contact City staff if you have concerns about specific dates such as graduation parties, family reunions, etc.
Ramsey County Projects
[https://www.ramseycounty.us/residents/roads-transportation/current-roadwork/2022-road-construction-maintenance]
Please visit Ramsey County’s project website for additional project information.
Xcel Energy - Northeast Metro Gas Project
[https://www.xcelenergynemetrogasproject.com]
Please visit Xcel Energy’s website for additional project information.
Please note that construction schedules are subject to change.
Other Roseville, Ramsey County and MnDOT projects can be found on the city’s construction projects webpage.
[http://www.cityofroseville.com/697/Construction-Projects]
* * * * * * *