Roseville Public Works Projects Updates
The following projects are ongoing in the City this week. Visit the individual project webpages for additional information. Please note that construction schedules are subject to change.
Pavement Management Project
[http://cityofroseville.com/pmp]
Important project dates:
In progress – Continue mill and paving operations throughout project areas, Lexington Avenue pathway restoration, and retaining wall construction on County Road C2
September – Stormwater Improvements on Simpson Street
[https://www.cityofroseville.com/3680/C2-Simpson-Underground-Storm]
Late September - Milling and Paving Burke Avenue, Simpson Street and County Road C2
As this project includes multiple neighborhoods, when the contractor starts work, you may not see them in your neighborhood right away. They may begin in a different area and work towards your street. Please contact City staff if you have concerns about specific dates such as graduation parties, family reunions, etc.
Ramsey County Projects
[https://www.ramseycounty.us/residents/roads-transportation/current-roadwork/2022-road-construction-maintenance]
Please visit Ramsey County’s project website for additional project information.
Xcel Energy - Northeast Metro Gas Project
[https://www.xcelenergynemetrogasproject.com]
Please visit Xcel Energy’s website for additional project information.
Please note that construction schedules are subject to change.
Other Roseville, Ramsey County and MnDOT projects can be found on the city’s construction projects webpage.
[http://www.cityofroseville.com/697/Construction-Projects]
* * * * * * *
This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:
http://www.cityofroseville.com/list.asp?mode=del [http://www.cityofroseville.com/list.asp?mode=del]