Roseville Public Works Construction Updates
2023 Pathway Project
[http://cityofroseville.com/3739/2023-Pathway-Project]
Lexington Avenue
Week of July 31 - Tree Trimming
August - Contractor working in other areas of the project
September - Grading and Wall Construction
End of September – Mid October: Pathway Paving, Concrete Ped Ramps
Marion Street
Week of July 31 - Tree Trimming
August 4 -16 - Curb removals and Utility Work
August 17 to September 4 - Grading and Concrete Sidewalk Construction
Week of September 4 - Roadway Milling and Paving
Cleveland Avenue
August/September - Small Utility Relocations - By Others
Late September to Mid-October: Retaining Wall and Pathway Construction
Please note that construction schedules are subject to change.
Other Roseville, Ramsey County and MnDOT projects can be found on the City’s Construction Projects webpage.
[http://www.cityofroseville.com/697/Construction-Projects]
* * * * * * *
This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:
http://www.cityofroseville.com/list.asp?mode=del [http://www.cityofroseville.com/list.asp?mode=del]