Roseville Public Works Construction Updates
County Road B Reconstruction (2024)
[cityofroseville.com/ctyrdb]
Neighborhood Meeting #5 will be held at Roseville City Hall, 2660 Civic Center Drive, from 4-6pm on Wednesday, May 29. There will not be a formal presentation nor any new layouts. However, staff will be available to answer questions about the project.
Construction Updates
Updates will be posted here throughout the project. Please sign up to receive notice of these updates (select "Public Works Projects Updates"). Dates below are anticipated, but subject to change:
Week of June 3 - Marked concrete curb and driveway sections will be removed. Pavement will be reclaimed where storm sewer will be installed. Areas will be filled with gravel so that access is maintained.
Week of June 10 - Storm sewer construction near and on Acorn Road should begin. Access will be maintained to properties, but driveway access may be limited. Staff will inform impacted residents in advance.
2024 Pavement Management Project
[cityofroseville.com/pmp]
Schedules
For schedule information for Eustis Street, St. Croix Street, St. Stephen Street, Fairways Lane, Fulham Street, Midland View Court, Acorn Road, Hwy 36 Service Drive, and Cleveland Service Drive, please visit the County Road B Reconstruction Project webpage [https://cityofroseville.com/3580/County-Road-B-Reconstruction-2024]
For all other areas, the proposed project schedule is shown below. Roseville Council actions are noted with “RV CC” and Falcon Heights Council actions are noted with “FH CC”:
Rose Place, William Street, Burke Avenue, Marion Street, Woodbridge Street, Skillman Avenue, Albemarle Street, and Giesmann Street Construction
Week of May 27 - complete concrete repairs
Week of June 3 - mill and overlay of road surface
Roselawn Construction
Week of May 27 - complete concrete repairs
Week of June 3 - mill and overlay of road surface
Week of June 10 – stripe road
Fall 2024 - FH CC Assessment Hearing
Sanitary Sewer Main Lining Project
[cityofroseville.com/sewerlining]
Schedule
The proposed project schedule is below. The schedule will be updated as construction dates are received from the contractor. Council
Week of May 27, 2024 – cleaning and lining work begins
October, 2024 – work is completed
Please note that construction schedules are subject to change.
Roseville Bike Plan
[cityofroseville.com/bikeplan]
We need your help identifying how we can make a bicycle network that is safe and comfortable for riders of all ages and abilities to use confidently! Visit the website to take the survey, share thoughts on a map, and sign up for updates for upcoming bike audits and workshops.
Other Roseville, Ramsey County and MnDOT projects can be found on the City’s Construction Projects webpage.
[http://www.cityofroseville.com/697/Construction-Projects]
* * * * * * *
This complimentary message is being sent to opt-in subscribers who might be interested in its content. If you do not wish to continue receiving these messages, please accept our apologies, and unsubscribe by visiting our website at:
http://www.cityofroseville.com/list.asp?mode=del [http://www.cityofroseville.com/list.asp?mode=del]